S.R. 201 Overnight Closure Scheduled This Weekend

For Immediate Release

S.R. 201 Overnight Closure Scheduled This Weekend

Lane restrictions also scheduled on I-15 at the Point of the Mountain, Bangerter Highway, and I-15 in Utah County 

SALT LAKE CITY (July 13, 2016) – The Utah Department of Transportation (UDOT) is scheduled to close S.R. 201 near the I-215 interchange Friday night, July 15, beginning at 9 p.m. Drivers should plan ahead and use I-80 as an alternate route.

 

Eastbound S.R. 201 will close beginning at 9 p.m. Friday, and then westbound S.R. 201 will close by midnight. S.R. 201 will open in both directions by Saturday, July 16, at 6 a.m. During this closure, crews will place new beams for temporary bridges on I-215.

 

This work is being completed as part of the I-215 reconstruction project, which will repave the freeway between S.R. 201 and 4700 South with new concrete, rebuild the bridges at the I-215/S.R. 201 interchange, and add new exit-only lanes in both directions.

 

Also this weekend, northbound I-15 is scheduled to be reduced to one lane from 2100 North in Lehi to 14600 South in Bluffdale for three nights – Friday, July 15; Saturday, July 16; and Sunday, July 17. Lane closures will start as early as 8 p.m. each night, with northbound I-15 reduced to one lane by midnight. All lanes will reopen by 10 a.m. on Saturday andSunday and by 5:30 a.m. on Monday. Crews will be paving and continuing bridge work as part of the I-15 widening project near the Point of the Mountain.

 

Other projects that drivers should plan for this week include:

 

I-15 in Provo – Lane restrictions are scheduled the nights of Wednesday, July 13, and Thursday, July 14, on I-15 near University Avenue (Exit 263) in Provo. On Wednesday night, southbound I-15 will be reduced to two lanes at 8 p.m., with all lanes scheduled to open Thursday at 6 a.m. Also that night, northbound I-15 is scheduled to be reduced to three lanes from 7 p.m. to midnight.

 

Then, on Thursday night, July 14, southbound I-15 is scheduled to be reduced to three lanes as early as 9 p.m., with all lanes reopening by Friday, July 15, at 6 a.m. These lane closures will allow crews to install new overhead signs for the Provo Westside Connector on I-15.  

 

Bangerter Highway at I-15 – The on-ramp from eastbound Bangerter Highway to southbound I-15 is scheduled to close from Friday, July 15, at 11 p.m., to Monday, July 18, at 6 a.m. Crews will be repairing the concrete pavement on the ramp. Eastbound drivers should get on northbound I-15, then use the 12300 South interchange to turn around onto southbound I-15.

 

I-15 in Lehi – Lane restrictions are scheduled on I-15 in Lehi near the Main Street (Exit 279) each night from Saturday, July 16, to Monday, July 18, while crews complete pavement repairs:

 

  • Northbound I-15 will be reduced to two lanes from Saturday, July 16, at 10 p.m. to Sunday, July 17, at 9 a.m. In addition, the northbound on-ramp from Main Street to I-15 will be closed during this time.
  • Southbound I-15 will be reduced to two lanes from Sunday, July 17, at 10 p.m., to Monday, July 18, at 6 a.m., and again from Monday, July 18, at 10 p.m., to Tuesday, July 19, at 6 a.m.

 

Construction schedules are weather-dependent and subject to change. For the latest information on traffic restrictions during construction, visit the UDOT Traffic website (udottraffic.utah.gov) or download the UDOT Traffic app for iPhone or Android. Drivers can also follow UDOT on social media including Twitter, Facebook, and Instagram.

 

-UDOT-

Media Contact:
John Gleason
UDOT Public Information Officer
jgleason@utah.gov
Cell: 801-560-7740

Plan ahead for delays on the July 4 weekend

UDOT engineers advise avoiding travel during heavy traffic times; construction to be suspended on most highway projects

 SALT LAKE CITY – The Utah Department of Transportation (UDOT) advises drivers to plan ahead for travel delays this July 4 weekend by avoiding heavy traffic times if possible. Although work will be suspended and lanes will be open on most Utah highways, existing restrictions will remain in place to protect the work zone and ensure safety on several major projects in Salt Lake, Davis, Utah, and Summit counties.

UDOT traffic engineers anticipate heaviest traffic this weekend on Thursday, July 2, between noon and 7 p.m., with highest overall traffic volumes expected around 3 p.m. A second period of high traffic is also expected from Saturday, July 4, at 10:30 p.m. to Sunday, July 5, at 12:30 a.m.

To help accommodate high traffic levels, UDOT will be adjusting the timing of traffic signals and ramp meters. UDOT is also partnering with Orem and Provo, as well as Brigham Young University, to help manage traffic to and from the Stadium of Fire event. Motorists attending the Stadium of Fire are encouraged to avoid construction on Orem Center Street, and use 800 North or University Parkway as an alternate.

Road construction projects that drivers should be aware of when planning their trips this weekend include:

I-15 at the Point of the Mountain
All four lanes are open in both directions on I-15. However, the northbound lanes have been split into two sections between S.R. 92 and 14600 South. Drivers wanting to exit at 14600 South need to stay to the right through the lane split. Due to narrowed and shifting lanes throughout the construction zone, the speed limit has been reduced to 55 miles per hour.

I-80 in Summit County
I-80 is reduced to one lane in each direction from the U.S. 40 interchange to Wanship in Summit County. All traffic has been shifted to the eastbound lanes, and the speed limit is reduced to 45 miles per hour. In addition, the westbound on- and off-ramps at Exit 150 (Tollgate/Promontory) are closed. To reduce delays, drivers should consider using I-84 through Ogden as an alternate route. These restrictions are scheduled to remain in place through fall 2015 while crews reconstruct the freeway with concrete pavement.

Drivers should remember to stay alert, use caution, and obey posted speed limits when traveling through construction zones in order to ensure safety.

Construction schedules are weather dependent and subject to change. For more information about these and other UDOT projects, visit udottraffic.utah.gov or download the UDOT Traffic app, available for iOS or Android devices.

With lane splits, closures, Utah drivers need to plan ahead

Lane splits at the Point of the Mountain, lane closures in Davis County may delay drivers  

SALT LAKE CITY — The Utah Department of Transportation (UDOT) advises drivers to plan ahead for travel delays on I-15 in Davis and Utah counties beginning as early as Saturday night. Crews will install a new lane split at the Point of the Mountain, and close lanes on I-15 in Davis County to allow concrete to cure.

The following is a brief description of road construction projects that drivers should be aware of this weekend (all schedules subject to change due to weather or equipment issues):

I-15 at the Point of the Mountain

A new lane split is scheduled to be in place on northbound I-15 at the Point of the Mountain starting as early as Sunday morning. The split will divide the northbound lanes into two sections while crews reconstruct the center lanes of the freeway. As part of this split, the two outside lanes will be shifted onto the new permanent pavement for the first time.

All four lanes will continue north on I-15 – however, drivers planning to exit at 14600 South will need to stay right. The lane split will allow UDOT to keep all four lanes open through construction along this busy section of I-15.

Once this split is in place, all four lanes will be reopened at S.R. 92 (currently, one northbound lane is closed at the interchange). To better control traffic merging onto I-15, the ramp meter for the northbound S.R. 92 on-ramp to I-15 will be turned on.

The lane split will work much like it does in Davis County, as shown in the video below.

 

I-15 in Davis County

Southbound I-15 is scheduled to be restricted to three lanes near 400 North in Bountiful for barrier work. Beginning as early as Friday, June 26, at 4 p.m., crews will close the right lane of southbound I-15. This restriction is scheduled to remain in place through Saturday, June 27, at 4 p.m. to allow the concrete to cure.

Northbound I-15 is scheduled to be restricted to three lanes near 2600 South in Bountiful this weekend. Beginning as early as Saturday, June 27, at 6 p.m., crews will close one northbound lane for bridge work. This restriction is scheduled to remain in place through Monday, June 29, at 6 a.m. Drivers should plan ahead for minor delays during this time, and consider using alternate routes such as Legacy Parkway.

Construction schedules are weather-dependent and subject to change. For more information about these and other UDOT projects, visit udottraffic.utah.gov or download the UDOT Traffic app, available for iOS or Android devices.

Delay data to help drivers “Rethink Your Commute”

DRAPER — As part of UDOT’s ongoing efforts to minimize the inconvenience of construction, the Traffic Operations Center (TOC) is posting a new set of travel data on the overhead variable message signs (VMS).

Starting today, commuters traveling on I-15 through The Point project at the Point of the Mountain will be able to see the difference in delay for the time of day that they are on the road, compared to earlier or later.

The Variable Message Sign on SB I-15 near 8200 South educates motorists on the best times to commute around The Point.

The Variable Message Sign on SB I-15 near 8200 South educates motorists on the best times to commute around The Point.

For example, a driver traveling from I-215 to Lehi Main Street at 5:15 p.m. would have to deal with average delays of nearly 25 minutes. But if that same driver traveled an hour earlier, she would only be delayed about 13 minutes.

A person could also reduce delays by driving later. Taking the same route, a driver could save ten minutes by traveling at 6:30 p.m. instead of 5:30.

Those ten minutes could be spent wrapping up a project at work, or watching the first inning of your kid’s baseball game – rather than stuck in traffic.

In addition to shifting your travel times, there are several other ways you can rethink your commute to avoid getting stuck in construction traffic. Consider TravelWise strategies like taking public transit, telecommuting or carpooling. Learn more at udot.utah.gov/rethink.

Data shows delay times can be decreased significantly by rethinking when you're on the road.

Data shows delay times can be decreased significantly by rethinking when you’re on the road.

This post was written by Christina Davis, Communications Manager on The Point project. 

UDOT releases 2015 top 15 construction projects list

SALT LAKE CITY — The Utah Department of Transportation (UDOT) announced today its top 15 road construction projects for 2015.

More than 180 construction projects are scheduled statewide this year, and motorists will need to plan accordingly. This season, UDOT is adding new lanes to freeways and highways, and building new roads to keep Utah moving. Crews will continue to perform maintenance on the state’s roads and bridges to ensure they remain in good condition and last as long as possible.

With two of the top projects located on Interstate 15, UDOT recommends motorists along the Wasatch Front rethink how they commute to reduce delays by carpooling, using transit, adjusting work schedules to leave earlier or stay later, or telecommuting.

The following is a list of the top 15 projects statewide in 2015:

1. I-15 The Point (Project Value $252 million)
Construction starts March 2015; scheduled completion fall 2016

UDOT’s largest project will widen I-15 to six lanes in each direction between 12300 South in Draper and state Route 92 in Lehi. The project will also reconstruct the interchange at 14600 South. Four lanes in each direction will remain open during daytime hours, but motorists should plan for delays due to lane shifts and other activities.

2. I-15 South Davis (Project Value $126.9 million)
Under construction; scheduled completion fall 2015

Last year’s largest construction project is scheduled for completion this year. Crews continue work to add Express Lanes on I-15 from North Salt Lake to Farmington. Work is also underway to reconstruct interchanges at 2600 South and 500 South in Bountiful as well as bridges at 1500 South and 400 North. Drivers can expect lane shifts as well as nighttime lane restrictions and surface street closures during construction.

SouthDavisConstruction

3. I-80, Silver Creek to Wanship (Project Value $43 million)
Construction resumes in April; scheduled completion fall 2015

Work will resume this spring to complete the reconstruction of eight miles of I-80 with new concrete pavement between US-40 and Wanship. In addition, two bridges over I-80 are scheduled to be reconstructed this summer. Long-term lane restrictions will last from April through the fall with a small number of overnight freeway closures to accommodate bridge work.

i-80 Silver Creek to Wanship

4. I-15 Beaver Climbing Lanes (Project Value $44 million)
Construction starts March 2015; scheduled completion November 2015

I-15 is being widened in two locations in central and southern Utah to add climbing lanes to enhance safety. Lane restrictions will be in place through much of the summer to allow crews to construct these new lanes. Motorists should plan ahead and allow extra travel time when traveling to and from St. George or Las Vegas.

Beaver Climbing lanes

5. SR-36 Reconstruction (Project Value $25.6 million)
Construction starts spring 2015; scheduled completion fall 2015

A 10-mile stretch of state Route 36 in Tooele County is being reconstructed with new pavement, curb/gutter/sidewalk, and drainage improvements. Construction is scheduled to begin as early as April, and will continue for several months. Drivers will need to watch for traffic shifts and various restrictions to accommodate the work.

SR 36 Tooele

6. I-15 Hill Field Road interchange and Thru-Turn Intersections (Project Value $28 million)
Construction starts spring 2015; scheduled completion fall 2016

The interchange at I-15 and Hill Field Road is being converted to a single-point urban interchange to improve traffic flow and reduce congestion in the area. This project will also construct new Thru-Turn Intersections on Hill Field Road on each side of I-15. Construction is scheduled to begin this spring and continue through 2016. Drivers should plan ahead for lane restrictions and traffic delays throughout construction.

7. Bangerter/Redwood Interchange (Project Value $42 million)
Under construction; scheduled completion July 2015

Crews are completing the new interchange at Bangerter Highway and Redwood Road. Temporary traffic patterns in the area will continue through the summer. When complete, the new freeway-style interchange will be similar to the one constructed at Bangerter Highway and 7800 South.

RedwoodBangerter

8. I-215, 300 East to Redwood Road (Project Value $14 million)
Construction starts July 2015; scheduled completion October 2015

This heavily-traveled section of I-215 is being reconstructed this year. Crews will be removing the top layer of asphalt and replacing it with new pavement, as well as installing drainage improvements. Motorists should plan for lane restrictions and moderate traffic delays.

9. US-40, SR-208 to Duchesne (Project Value $14.6 million)
Construction starts spring 2015; scheduled completion August 2015

UDOT will be removing the top layer of asphalt and repaving 18 miles of US-40 in Duchesne County. This project will prolong the life of the road and provide a smoother ride for drivers. Lane restrictions and minor traffic delays are possible through the summer.

US 40 Duchesne

10. SR-108, 2000 West in Roy/Ogden (Project Value $16.9 million)
Under construction; scheduled completion summer 2015 

A 4.5-mile section of state Route 108 in Davis and Weber counties is being widened and reconstructed. One lane in each direction will be added, as well as curb, gutter and sidewalk. Motorists should plan ahead for lane restrictions and temporary access restrictions at intersections.

SR 108 Weber County

11. Provo Westside Connector/Vineyard Connector (Project Value $21.1/$13.7 million)
Under construction; scheduled completion spring 2016

Two new arterial roads are being constructed to serve the fast-growing areas of Provo and Vineyard in Utah County. Construction has already begun on these roads, and motorists using nearby or connecting streets should watch for trucks and other equipment.

ProvoWestside

 

For more information on the Vineyard connector, please e-mail udotregion3@utah.gov or call our region hotline 801-830-9304.

12. U.S. 89/State Street, Sandy and Draper (Project Value $2.7 million)
Construction starts summer 2015; scheduled completion fall 2015

Two sections of State Street – from 8000 South to 9000 South, and from 11400 South to 11800 South – will be repaved this summer. Work will primarily take place during nighttime hours, and motorists should expect lane restrictions and business access restrictions during this time.

US 89 Sandy:Draper State Street

13. U.S. 89/Harrison Boulevard intersection (Project Value $6.3 million)
Construction starts May 2015; scheduled completion September 2015

UDOT will realign the intersection of US-89 with Harrison Boulevard to improve traffic flow and will install additional safety improvements in the area. U.S. -89 will also be widened near the intersection. Occasional lane closures will be necessary to complete the work, and motorists should expect additional congestion due to construction.

14. SR-7, Warner Valley to Washington Dam Road (Project Value $21 million)
Under construction; scheduled completion December 2015

Construction continues to extend state Route 7 (Southern Parkway) near the St. George Airport. This extension of the new highway will help improve travel between the new airport and area recreation sites including Zion National Park and Sand Hollow Reservoir.

Southern Parkway

15. Antelope Drive, 2200 West to University Park Boulevard (Project Value $8 million)
Under construction; scheduled completion May 2015

Antelope Drive is being widened near the I-15 interchange to improve traffic flow and enhance safety in the area. Additional turn lanes are being constructed near the entrance to Davis Hospital and Medical Center. Lane restrictions and occasional delays are expected, but two lanes in each direction will remain open on Antelope Drive at all times.

AntelopeDrive

UDOT wants motorists to be in the know regarding construction projects and traffic delays. The following tools are available to provide information about projects and traffic conditions statewide:

UDOT Traffic App — The UDOT Traffic app delivers traffic info directly to motorists by incorporating the best and most up-to-date information from the UDOT Traffic Operations Center, including real-time traffic conditions, construction alerts, crash information and road weather conditions. The UDOT Traffic app is free and available for download in the Apple App Store and Android Market for tablets and smart phones.

Interactive UDOT Traffic Website — The website, http://udottraffic.utah.gov, features an interactive map identifying the locations of UDOT projects statewide. Additional information is provided for each project, including the construction schedule, expected travel delays and the project benefits. The public can also subscribe to an RSS feed on the site to receive real-time updates for the projects that affect them most.

UDOT social media — UDOT offers an official Twitter feed and Facebook page; UDOT Traffic and its four regions statewide also operate Twitter accounts. Motorists can find a list of these feeds at twitter.com/UtahDOT where they can receive regular updates on road construction and traffic conditions.