Tag Archives: South Davis Project

With lane splits, closures, Utah drivers need to plan ahead

Lane splits at the Point of the Mountain, lane closures in Davis County may delay drivers  

SALT LAKE CITY — The Utah Department of Transportation (UDOT) advises drivers to plan ahead for travel delays on I-15 in Davis and Utah counties beginning as early as Saturday night. Crews will install a new lane split at the Point of the Mountain, and close lanes on I-15 in Davis County to allow concrete to cure.

The following is a brief description of road construction projects that drivers should be aware of this weekend (all schedules subject to change due to weather or equipment issues):

I-15 at the Point of the Mountain

A new lane split is scheduled to be in place on northbound I-15 at the Point of the Mountain starting as early as Sunday morning. The split will divide the northbound lanes into two sections while crews reconstruct the center lanes of the freeway. As part of this split, the two outside lanes will be shifted onto the new permanent pavement for the first time.

All four lanes will continue north on I-15 – however, drivers planning to exit at 14600 South will need to stay right. The lane split will allow UDOT to keep all four lanes open through construction along this busy section of I-15.

Once this split is in place, all four lanes will be reopened at S.R. 92 (currently, one northbound lane is closed at the interchange). To better control traffic merging onto I-15, the ramp meter for the northbound S.R. 92 on-ramp to I-15 will be turned on.

The lane split will work much like it does in Davis County, as shown in the video below.

 

I-15 in Davis County

Southbound I-15 is scheduled to be restricted to three lanes near 400 North in Bountiful for barrier work. Beginning as early as Friday, June 26, at 4 p.m., crews will close the right lane of southbound I-15. This restriction is scheduled to remain in place through Saturday, June 27, at 4 p.m. to allow the concrete to cure.

Northbound I-15 is scheduled to be restricted to three lanes near 2600 South in Bountiful this weekend. Beginning as early as Saturday, June 27, at 6 p.m., crews will close one northbound lane for bridge work. This restriction is scheduled to remain in place through Monday, June 29, at 6 a.m. Drivers should plan ahead for minor delays during this time, and consider using alternate routes such as Legacy Parkway.

Construction schedules are weather-dependent and subject to change. For more information about these and other UDOT projects, visit udottraffic.utah.gov or download the UDOT Traffic app, available for iOS or Android devices.

Plan ahead for delays in Davis County

Lane restrictions, freeway closure scheduled for new bridge construction and concrete maintenance

SALT LAKE CITY — The Utah Department of Transportation (UDOT) advises drivers to plan ahead for delays on I-15 in Davis County this weekend. Crews are scheduled to set beams on the new 400 North bridge in Bountiful and complete concrete maintenance on the bridge over the railroad tracks on I-215 in North Salt Lake. Both projects will require significant lane restrictions.

The following is a brief description of road construction projects that drivers should be aware of this weekend (all schedules subject to change due to weather or equipment issues):

I-15 in Davis County

I-15 will be closed in both directions overnight Saturday, June 6, while crews build a new bridge at 400 North in Bountiful.

Southbound I-15 is scheduled to close at 500 West as early as 11 p.m. During this time northbound I-15 will remain open, but will be reduced to one lane. Once the new beams are set over the southbound lanes, crews will reopen one southbound lane and I-15 will be closed at 400 North. All lanes are schedule to reopen by 11 a.m. Sunday.

UDOT recommends Legacy Parkway as an alternate route. 400 North will remain closed at I-15 until project completion later this summer. The new bridge will feature improved sidewalks, wider shoulders and a higher barrier between traffic and pedestrians.

I-215 in North Salt Lake

Drivers should plan ahead for heavy delays near the I-215 ramps on I-15 in North Salt Lake. I-215 has been reduced to one lane in each direction while crews complete concrete maintenance on the bridge over the railroad tracks. This restriction will remain in place 24 hours per day for up to two months. UDOT recommends drivers use Legacy Parkway as an alternate.

Construction schedules are weather dependent and subject to change. For more information about these and other UDOT projects, visit udottraffic.utah.gov or download the UDOT Traffic app, available for iOS or Android devices.

 

Major Delays Expected on I-15 this Weekend in Davis, Utah Counties

SALT LAKE CITY — The Utah Department of Transportation (UDOT) advises drivers to plan ahead for significant traffic restrictions on I-15 in Davis and Utah counties beginning as early as Saturday night. Crews will be demolishing a bridge at 400 North in Bountiful, and completing concrete pavement maintenance in Springville. Additional restrictions are also scheduled to begin on I-80 in Summit County as early as Saturday morning.

The following is a brief description of road construction projects that drivers should be aware of this weekend (all schedules subject to change due to weather or equipment issues):

I-15 in Davis County

I-15 is scheduled to close in both directions on Saturday, April 18, as early as 11 p.m. while crews demolish a bridge at 400 North in Bountiful. The freeway will be closed at the following locations:

  • Southbound I-15 will be closed between the Legacy Parkway/Park Lane interchange in Farmington and 400 North in Bountiful, and all southbound traffic will be diverted to Legacy Parkway. The southbound I-15 on-ramps at all interchanges in this area will also be closed.
  • Northbound I-15 will be closed at 400 North (Exit 317) in Bountiful. Northbound traffic will be diverted onto 400 North, then back onto the freeway via 500 West.

The freeway is scheduled to reopen by Sunday, April 19, at 11 a.m. Drivers in both directions are advised to use Legacy Parkway as an alternate route.

View Alternate routes for this weekend, as Interstate 15 will be closed from Farmington to Bountiful.

View Alternate routes for this weekend, as Interstate 15 will be closed from Farmington to Bountiful.

I-15 in Utah County

Southbound I-15 is scheduled to be reduced to one lane between 1400 North (Exit 261) and 400 South (Exit 260) in Springville on Saturday, April 18, as early as 9 p.m. for concrete pavement maintenance. These restrictions are scheduled to remain in place through Monday, April 20, at 7 a.m., when an additional lane will reopen.

During this time, drivers should plan ahead for severe traffic delays of more than an hour on Sunday, April 19, between 10 a.m. and 10 p.m. US-89 through Provo and Springville should be considered as an alternate route. In addition, UDOT recommends that drivers adjust their schedules to avoid travel on southbound I-15 during this time if possible.

Following these lane restrictions, the southbound lanes on I-15 in this area are scheduled to be split into two sections on Monday, April 20, as early as 12 p.m. This lane split is expected to remain in place through Thursday, April 23, at 5 a.m. to allow concrete pavement to cure. Drivers wanting to use exits 261 (1400 North) or 260 (400 South) in Springville will need to stay in the right lanes.

This work is being completed under warranty as part of the I-15 CORE project at no additional cost to taxpayers.

View alternate routes from Provo to Springville, as Interstate 15 will be closed for much of the weekend.

View alternate routes from Provo to Springville, as Interstate 15 will be closed for much of the weekend.

I-15 in Salt Lake County

Southbound I-15 is scheduled to be reduced to four lanes north of the 10600 South interchange beginning as early as Saturday, April 18, at 10 p.m. These restrictions are scheduled to remain in place through Sunday, April 19, at noon while crews complete concrete maintenance. This work is being completed at night to minimize traffic delays.

I-80 in Summit County

I-80 is scheduled to be reduced to one lane in each direction from the U.S. 40 interchange to Wanship as early as Saturday morning, April 18. All traffic will be shifted to the eastbound lanes, and the speed limit will be reduced to 45 miles per hour. In addition, the westbound on- and off-ramps at Exit 150 (Tollgate/Promontory) will both be closed. These restrictions are scheduled to remain in place through fall 2015.

Crews are completing the second phase of a project to reconstruct I-80 in this area with new concrete pavement. Last year, work was completed in the eastbound lanes, and this season crews are reconstructing the westbound lanes.

Construction schedules are weather-dependent and subject to change. For more information about these and other UDOT projects, visit udottraffic.utah.gov or download the UDOT Traffic app, available for iOS or Android devices.

 -30-

UDOT releases 2015 top 15 construction projects list

SALT LAKE CITY — The Utah Department of Transportation (UDOT) announced today its top 15 road construction projects for 2015.

More than 180 construction projects are scheduled statewide this year, and motorists will need to plan accordingly. This season, UDOT is adding new lanes to freeways and highways, and building new roads to keep Utah moving. Crews will continue to perform maintenance on the state’s roads and bridges to ensure they remain in good condition and last as long as possible.

With two of the top projects located on Interstate 15, UDOT recommends motorists along the Wasatch Front rethink how they commute to reduce delays by carpooling, using transit, adjusting work schedules to leave earlier or stay later, or telecommuting.

The following is a list of the top 15 projects statewide in 2015:

1. I-15 The Point (Project Value $252 million)
Construction starts March 2015; scheduled completion fall 2016

UDOT’s largest project will widen I-15 to six lanes in each direction between 12300 South in Draper and state Route 92 in Lehi. The project will also reconstruct the interchange at 14600 South. Four lanes in each direction will remain open during daytime hours, but motorists should plan for delays due to lane shifts and other activities.

2. I-15 South Davis (Project Value $126.9 million)
Under construction; scheduled completion fall 2015

Last year’s largest construction project is scheduled for completion this year. Crews continue work to add Express Lanes on I-15 from North Salt Lake to Farmington. Work is also underway to reconstruct interchanges at 2600 South and 500 South in Bountiful as well as bridges at 1500 South and 400 North. Drivers can expect lane shifts as well as nighttime lane restrictions and surface street closures during construction.

SouthDavisConstruction

3. I-80, Silver Creek to Wanship (Project Value $43 million)
Construction resumes in April; scheduled completion fall 2015

Work will resume this spring to complete the reconstruction of eight miles of I-80 with new concrete pavement between US-40 and Wanship. In addition, two bridges over I-80 are scheduled to be reconstructed this summer. Long-term lane restrictions will last from April through the fall with a small number of overnight freeway closures to accommodate bridge work.

i-80 Silver Creek to Wanship

4. I-15 Beaver Climbing Lanes (Project Value $44 million)
Construction starts March 2015; scheduled completion November 2015

I-15 is being widened in two locations in central and southern Utah to add climbing lanes to enhance safety. Lane restrictions will be in place through much of the summer to allow crews to construct these new lanes. Motorists should plan ahead and allow extra travel time when traveling to and from St. George or Las Vegas.

Beaver Climbing lanes

5. SR-36 Reconstruction (Project Value $25.6 million)
Construction starts spring 2015; scheduled completion fall 2015

A 10-mile stretch of state Route 36 in Tooele County is being reconstructed with new pavement, curb/gutter/sidewalk, and drainage improvements. Construction is scheduled to begin as early as April, and will continue for several months. Drivers will need to watch for traffic shifts and various restrictions to accommodate the work.

SR 36 Tooele

6. I-15 Hill Field Road interchange and Thru-Turn Intersections (Project Value $28 million)
Construction starts spring 2015; scheduled completion fall 2016

The interchange at I-15 and Hill Field Road is being converted to a single-point urban interchange to improve traffic flow and reduce congestion in the area. This project will also construct new Thru-Turn Intersections on Hill Field Road on each side of I-15. Construction is scheduled to begin this spring and continue through 2016. Drivers should plan ahead for lane restrictions and traffic delays throughout construction.

7. Bangerter/Redwood Interchange (Project Value $42 million)
Under construction; scheduled completion July 2015

Crews are completing the new interchange at Bangerter Highway and Redwood Road. Temporary traffic patterns in the area will continue through the summer. When complete, the new freeway-style interchange will be similar to the one constructed at Bangerter Highway and 7800 South.

RedwoodBangerter

8. I-215, 300 East to Redwood Road (Project Value $14 million)
Construction starts July 2015; scheduled completion October 2015

This heavily-traveled section of I-215 is being reconstructed this year. Crews will be removing the top layer of asphalt and replacing it with new pavement, as well as installing drainage improvements. Motorists should plan for lane restrictions and moderate traffic delays.

9. US-40, SR-208 to Duchesne (Project Value $14.6 million)
Construction starts spring 2015; scheduled completion August 2015

UDOT will be removing the top layer of asphalt and repaving 18 miles of US-40 in Duchesne County. This project will prolong the life of the road and provide a smoother ride for drivers. Lane restrictions and minor traffic delays are possible through the summer.

US 40 Duchesne

10. SR-108, 2000 West in Roy/Ogden (Project Value $16.9 million)
Under construction; scheduled completion summer 2015 

A 4.5-mile section of state Route 108 in Davis and Weber counties is being widened and reconstructed. One lane in each direction will be added, as well as curb, gutter and sidewalk. Motorists should plan ahead for lane restrictions and temporary access restrictions at intersections.

SR 108 Weber County

11. Provo Westside Connector/Vineyard Connector (Project Value $21.1/$13.7 million)
Under construction; scheduled completion spring 2016

Two new arterial roads are being constructed to serve the fast-growing areas of Provo and Vineyard in Utah County. Construction has already begun on these roads, and motorists using nearby or connecting streets should watch for trucks and other equipment.

ProvoWestside

 

For more information on the Vineyard connector, please e-mail udotregion3@utah.gov or call our region hotline 801-830-9304.

12. U.S. 89/State Street, Sandy and Draper (Project Value $2.7 million)
Construction starts summer 2015; scheduled completion fall 2015

Two sections of State Street – from 8000 South to 9000 South, and from 11400 South to 11800 South – will be repaved this summer. Work will primarily take place during nighttime hours, and motorists should expect lane restrictions and business access restrictions during this time.

US 89 Sandy:Draper State Street

13. U.S. 89/Harrison Boulevard intersection (Project Value $6.3 million)
Construction starts May 2015; scheduled completion September 2015

UDOT will realign the intersection of US-89 with Harrison Boulevard to improve traffic flow and will install additional safety improvements in the area. U.S. -89 will also be widened near the intersection. Occasional lane closures will be necessary to complete the work, and motorists should expect additional congestion due to construction.

14. SR-7, Warner Valley to Washington Dam Road (Project Value $21 million)
Under construction; scheduled completion December 2015

Construction continues to extend state Route 7 (Southern Parkway) near the St. George Airport. This extension of the new highway will help improve travel between the new airport and area recreation sites including Zion National Park and Sand Hollow Reservoir.

Southern Parkway

15. Antelope Drive, 2200 West to University Park Boulevard (Project Value $8 million)
Under construction; scheduled completion May 2015

Antelope Drive is being widened near the I-15 interchange to improve traffic flow and enhance safety in the area. Additional turn lanes are being constructed near the entrance to Davis Hospital and Medical Center. Lane restrictions and occasional delays are expected, but two lanes in each direction will remain open on Antelope Drive at all times.

AntelopeDrive

UDOT wants motorists to be in the know regarding construction projects and traffic delays. The following tools are available to provide information about projects and traffic conditions statewide:

UDOT Traffic App — The UDOT Traffic app delivers traffic info directly to motorists by incorporating the best and most up-to-date information from the UDOT Traffic Operations Center, including real-time traffic conditions, construction alerts, crash information and road weather conditions. The UDOT Traffic app is free and available for download in the Apple App Store and Android Market for tablets and smart phones.

Interactive UDOT Traffic Website — The website, http://udottraffic.utah.gov, features an interactive map identifying the locations of UDOT projects statewide. Additional information is provided for each project, including the construction schedule, expected travel delays and the project benefits. The public can also subscribe to an RSS feed on the site to receive real-time updates for the projects that affect them most.