Tag Archives: I15

I-215, I-15 Freeway Closures Scheduled Sunday and Monday

Drivers on I-215 and i-15 through Salt Lake City be warned, several closures over the weekend may impact travel. The closures will primarily be at night, but drivers should still be aware and plan for alternate routes if they’ll be going through those areas.

I-215 is scheduled to be closed in both directions near 600 South on Sunday, June 26, at 7 a.m.

The freeway will be closed for approximately 20 minutes while Rocky Mountain Power crews hang new power lines across the road. Drivers heading to the Salt Lake City International Airport should allow extra time or consider using I-15 to I-80 as an alternate route.

I-15 in Springville will be closed on Monday night, June 27. Crews are scheduled to close all northbound lanes on I-15 at the 1400 North interchange (Exit 261) around midnight to install the crossbar for a new overhead message sign. All northbound lanes are expected to reopen by Tuesday, June 28, at 2 a.m. During this closure, all traffic will be detoured onto S.R. 75. Detour signs will direct drivers back to northbound I-15 via U.S. 89 and 1860 South in Provo.

In addition, UDOT advises drivers to plan ahead for the following projects:

I-80, Salt Lake City: Eastbound I-80 will be reduced to one lane, and westbound I-80 will be reduced to three lanes, between 1300 East and State Street for pavement repairs on Friday, Saturday and Sunday nights during the following times:

Friday, June 24, at 8 p.m. to Saturday, June 25, at 9 a.m.
Saturday, June 25, at 8 p.m. to Sunday, June 26, at 10 a.m.
Sunday, June 26, at 7 p.m. to Monday, June 27, at 5 a.m.

I-215 West Belt, Salt Lake City: The ramp from southbound I-215 to eastbound S.R. 201 is scheduled to close for up to 30 days beginning on Monday, June 27, as early as 1 a.m. Drivers are encouraged to plan ahead and use alternate routes, such as I-80.

During the closure, crews will reconstruct the ramp, completely removing the existing pavement and replacing it with new concrete. This work is being completed as part of the I-215 reconstruction project, which will repave the freeway between S.R. 201 and 4700 South with new concrete and add new exit-only lanes in both directions.

Construction schedules are weather-dependent and subject to change. For additional information on traffic restrictions during construction, visit the UDOT Traffic website (udottraffic.utah.gov) or download the UDOT Traffic app for iPhone or Android. Drivers can also follow UDOT on social media including Twitter, Facebook, and Instagram.